West Fremont, St. Francis Water Main Improvements

Project Scope: The project consists of installing approximately 5,500 LF of 8” DIP, and 30 LF of 8” FPVC to replace existing cast iron and asbestos cement pipe, cathodic protection of newly installed water main, installation of 2 combination air valves, 14 fire hydrants, 21 service connections of varying sizes, existing water main/appurtenance abandonments, various surface restorations including slurry seal (~70,000 SF), restriping, among other appurtenance work as identified in the bid schedule.
Plans (click to expand/collapse)