CN - 2014 Tiburon Pipeline Replacement Project

This contract is for furnishing labor and equipment for the installation of 3,490 linear feet of 8-inch, 6-inch, and 4-inch welded steel pipe with valves, fittings, pipe disinfection, and appurtenances. The work to be done is located in the Town of Tiburon within the County of Marin, California.

Status

Bidding Closed

Bid Date5/16/24 10:00am

Company & Contacts

Marin Water
Ava Pridgeon  
415-945-1575

Location

Marin Water

Engineers Estimate : $2,160,000